9099 Holly Rd
Directions Grand Blanc, MI 48439

  • Sales: (866) 790-4895
  • Service: 877-289-3914

Alternative Routes For Our Valued Customers

 
Estimated Starting Date:
Tuesday, July 11, 2017

Estimated Completion Date:
October 2017

Traffic Restrictions:
Beginning July 11, one lane will be closed on northbound I-75 near Holly Road to accommodate staging for the project. Following the July 4 holiday, the northbound I-75 exit ramp (Exit 108) to Holly Road will be closed to traffic and detoured via Dixie Highway (Saginaw Street/Exit 106) and Baldwin Road back to Holly Road. We also suggest taking (Grange Hall Road/Exit 101) to Holly Road. 

Throughout the project, Holly Road traffic will be maintained with shoulder and single-lane closures.

Project:
The Michigan Department of Transportation (MDOT) will invest $3.1 million to reconstruct the northbound I-75 ramps at Holly Road interchange. Work includes reconstructing the existing ramps and adding a second northbound I-75 entrance ramp.
false false